Dock, Seawall, Dredge/Fill and Water-Dependent Approval Routing — Hillsborough County

countywideStatewidefederalUnincorporated Countytampaplant-citytemple-terrace

Route docks, boat lifts, seawalls, shoreline stabilization, dredging, filling, and other water-dependent work through every applicable local, EPC, state, submerged-lands, and federal review. Project location, ownership, wetlands and surface-water impacts, navigation, scope, and authorization type determine which approvals apply; no one approval is represented as satisfying the others.

Who needs this

Waterfront owners, associations, contractors, marinas, developers, and design professionals planning new, replacement, repair, maintenance, dredge/fill, shoreline, dock, lift, seawall, or related work in Hillsborough County.

Steps

  1. 1

    Confirm parcel jurisdiction, waterfront ownership, and project scope

    Resolve whether the upland parcel is in unincorporated Hillsborough, Tampa, Plant City, or Temple Terrace; identify the affected waterbody, wetlands, submerged-land ownership, easements, navigation and access conditions; and distinguish repair, replacement, new work, dredging, filling, shoreline stabilization, dock, lift, seawall, marina, or other scope.

    maps.hillsboroughcounty.org/MapHillsborough/MapHillsborough.
  2. 2

    Ask the local building and zoning authority what it requires

    Use the responsible County or city authority for upland zoning, setbacks, structural, electrical, right-of-way, floodplain, historic, utility, site, and building approvals. A mailing city or state/federal authorization does not determine local jurisdiction or replace local permits.

    hcfl.gov/businesses/hillsgovhub
  3. 3

    Obtain an EPC wetlands determination

    Consult the Environmental Protection Commission of Hillsborough County for the current wetlands permit, authorization, or exemption path. Provide the project location and plans so EPC can determine jurisdiction and the appropriate review; this workflow does not assume every activity is permitted or exempt.

    epchc.org/divisions/wetlands/permits-exemptions
  4. 4

    Determine Florida DEP ERP and submerged-lands authorization

    Confirm whether the work needs an Environmental Resource Permit, qualifies for a current exemption or general authorization, and requires separate authorization for state-owned submerged lands. Use DEP's current project-specific path rather than borrowing a Pinellas County permit or exemption.

    floridadep.gov/water/submerged-lands-environmental-resources
  5. 5

    Confirm federal Department of the Army authorization

    Ask the U.S. Army Corps of Engineers Jacksonville District whether the proposed work affects federal jurisdiction and whether it is covered by a current general authorization or needs another Department of the Army permit. Do not assume a Pinellas-specific or statewide general permit covers a Hillsborough project without confirmation.

    saj.usace.army.mil/Missions/Regulatory/
  6. 6

    Resolve other location- and resource-specific reviews

    Confirm mangrove, protected-species, water-quality, navigation, port, public-land, coastal, floodplain, utility, archaeological, access, and neighboring-property requirements when applicable. An exemption or approval from one authority is not evidence that another authority has approved the work.

    epchc.org/
  7. 7

    Submit coordinated plans and pay authority-specific fees

    Use a consistent site survey and signed/sealed plans where required, while submitting each authority's current forms, ownership/authorization evidence, resource information, contractor/design credentials, and calculated fees. Sequence or concurrency must be confirmed with the reviewing authorities.

    floridadep.gov/water/submerged-lands-environmental-resources
  8. 8

    Wait for every required issuance and complete inspections

    Do not begin regulated work until all required local, EPC, state, submerged-lands, federal, and companion approvals are effective. Follow permit conditions, schedule assigned inspections, and complete closeout with each issuing authority.

    tampa.gov/construction-services

Requirements

  • Confirm parcel jurisdiction and affected water/resource ownership.
  • Obtain project-specific local building and zoning determinations.
  • Obtain EPC wetlands determination or authorization.
  • Confirm Florida DEP ERP and state-owned submerged-lands requirements.
  • Confirm U.S. Army Corps authorization.
  • Resolve conditional resource, navigation, floodplain, utility, port, and access reviews.
  • Comply with every permit condition and inspection requirement.

Documents

  • Property and waterfront ownership or authorization records
  • Boundary/topographic/bathymetric survey and site plan as required
  • Existing and proposed dock, lift, seawall, shoreline, dredge/fill, structural, electrical, and construction plans
  • Wetland, surface-water, submerged-land, navigation, resource, and impact information required by reviewing authorities
  • Contractor and design-professional credentials as required
  • Local, EPC, state, federal, inspection, and closeout records

Fees

Good to know

Local, EPC, Florida DEP, state-owned submerged-lands, and U.S. Army Corps reviews are distinct; one approval does not satisfy the others.No Pinellas County Water and Navigation rule, fee, portal, or county-specific general permit is copied into Hillsborough.An authority must confirm exemption or general-permit eligibility for the actual project; the workflow does not infer it from a project label.The official EPC and U.S. Army Corps pages returned HTTP 403 to the September 24, 2026 research client; that response is disclosed and is not treated as proof that either authority or permit path is unavailable. Florida DEP and the four local authority sources remained reachable.